(Issued
vide Energy Deptt. letter no. F.20 (4) Energy/2004 dated 25.10.2004 and amended
vide
letters
of even nos. dated 10.3.2005, 16.7.05, 18.8.05, 24.2.06, 30-11-06 and 19-1-07)
1. Objectives:
|
1.1
Whereas with a view to promote generation of power from non-conventional
energy sources, Government of Rajasthan promulgated a Policy on 11.3.1999.
This Policy known as "Policy for Promoting Generation of Power
through Non-Conventional Energy Sources" ended on 31st March, 2004.
A separate Policy was, however, issued on 4th February, 2000 exclusively
for promoting generation of electricity from wind. This Policy known
as "Policy for Promotion of Electricity Generation from Wind"
too ended on 31st March, 2004. During the currency of Wind Policy 2000
a new Policy was promulgated in April 2003 for period up to 31st March,
2009. |
|
1.4
And whereas, among the non-conventional sources of energy, Solar, Wind, Mini-Small
hydel and Bio-mass have good potential for generation of electricity in Rajasthan
and after having gathered the experiences from the earlier policies and identifying
the impediments in the process of generation of electricity from non-conventional
sources, State Government has decided to issue a comprehensive Policy for
generation of electricity from various sources of non-conventional energy
which offers solution to various problems faced by developers, investors and
utilities, this Policy is being promulgated.
2. Title and enforcement:
2.1 This Policy will be known as Policy for Promoting
Generation of Electricity through Non-Conventional Energy Sources 2004.
2.2 The Policy will come into operation with
effect from 25.10.2004 and will remain in force until superseded or modified
by another Policy.
2.3 The amendments made in the Policy vide letters
of Energy Department no. F.20(4)Energy/2004 dated 10.3.2005, 16.7.05, 18.8.05,
24.2.06, 30-11-06 and 19-1-07 shall come into effect from the date they were
introduced or as specified below.
3. Definitions:-
3.1 Following expressions used in the Policy
would have meanings assigned to them as defined hereunder:-
(i)
"Act" means Electricity Act 2003 (Central Act No. 36 of 2003)
. |
![]() |
(vi)
"DLC" means 'District Level Committee' to fix the price of land
for purposes of registration.
(vii) "Discom" means a distribution licensee, such as Discom Jaipur,
Discom Jodhpur and Discom Ajmer.
(viii) "Financial year" means year starting on 1st April of Calender
year and ending on 31st March of next calendar year.
(ix) "Investor" A person investing for generation of electricity
from non-conventional sources of energy.
(x) "Independent Power Producer" (IPP) : A single investor who also
develops the wind farm.
(xi) "IREDA" means Indian Renewable Energy Development Agency.
(xii) "Licensee" means a person who has been granted license under
Section 14 of the Act.
(xiii) "Manufacturer" means manufacturer of Non-conventional Energy
based power plant.
(xiv) "MNRE" means Ministry of New and Renewable Energy Sources,
a Central Government Ministry promoting the use of Non-conventional Energy
Sources in India.
(xv) "Person" Person means an individual or a firm/company registered
under the Companies Act, 1956.
(xvi) "Power Producer" means investors/ developers generating grid-grade
electricity from Non-conventional Energy Sources.
(xvii) "Pooling Station" means sub-station developed by the developer
for interface with the receiving station.
(xviii) "Power" means electricity produced using the non-conventional
sources of energy.
(xix) "Policy-1999" means Policy for Promoting Generation of Power
through Non-Conventional Energy Sources issued on 11th March, 1999.
(xx) "Policy-2000" means Policy for Promoting Generation of Power
from Wind issued on 4th February, 2000.
(xxi) "Policy-2003" means Policy for Promotion of Electricity Generation
from Wind issued on 30th April, 2003.
(xxii) "PLF" means Plant Load Factor
(xxiii) "PPA" means Power Purchase Agreement
(xxiv) "Receiving Station" means EHV Sub-Station developed by RVPNL/Discom
for evacuation of power generated from Non-conventional Energy Sources.
(xxv) "RERC" means 'Rajasthan Electricity Regulatory Commission'.
(xxvi) "RREC" means Rajasthan Renewable Energy Corporation.
(xxvii) "RIICO" means Rajasthan Industrial & Investment Corporation.
(xxviii) "RVPN" means the Rajasthan Vidyut Prasaran Nigam.
(xxix) Solar Plant: means a power plant or system utilizing solar thermal
energy through solar photo-voltaic or concentrated solar thermal devices including
its integration into conventional fossil fuel for generation of electricity.
(xxx) "State" and "Government" means, respectively, the
State of Rajasthan and the Government of Rajasthan.
(xxxi) "WBA" means Wheeling and Banking Agreement.

3.2 The terms not defined above will have their
usual meaning.
4. Use of power for captive purposes/sale:
4.1 The Power Producers may use the power for
captive consumption or for sale to consumers/licensees including Discoms.
4.2 The cap on purchase of energy from power
generated through Non Conventional Energy Sources shall be in accordance with
that specified by the Rajasthan Electricity Regulatory Commission.
5. Grid Interfacing:
|
5.1 Except in case of
solar power not exceeding 220 KW the grid interfacing arrangements for
power using non-conventional sources of energy will be made by Developer/
RVPN/ Discom as under:- |
![]() |
shall
be developed and maintained by the Power Producer as per the specifications
and requirements of the RVPN/ Discom, and the entire cost for this will be
borne by the Power Producer.
5.1.2 Receiving Station
RVPN/Discom shall finalise the location of receiving station in consultation
with RREC on which the electricity generated will be received at minimum 33
KV level. For creation of proper facility for receiving power, the Power Producer
shall pay Rs. 2 lacs per MW to RVPN/ Discom as the case may be.
Provided that no grid connectivity charges shall be paid by solar and other
(except wind & biomass) power plants up to total installed capacity of
50 MW in the State.
|
5.1.3 Transmission from
Pooling Station to Receiving Station: |
![]() |
5.3
The Power Producer shall install metering device at the receiving station
at his own cost. Such metering device must conform to standards of metering
code.
5.4 The Power Producer shall install necessary
current limiting devices such as Thyristor in the generating equipment. Capacitors
of sufficient rating shall also be provided in the Wind Farm to ensure that
the average power factor is maintained as per requirements of State Load Despatch
Centre, measured at metering point of the Wind Farm.
5.5 The Power Producer shall comply with Grid
Code including Load Despatch and System Operation Code, Metering Code, Protection
Code, Safety Code etc. as applicable from time to time in the State of Rajasthan.

6. Wheeling and Banking:
6.1 Except in case of power sold to Discoms,
the Power Producer shall pay wheeling charges @ 10% of the energy billed into
the grid irrespective of the distance from the generating station and such
charges will be inclusive of the T&D losses.
Provided that in respect of third party sale and / or captive use for which
PPAs are signed after March 31, 2007, the transmission, wheeling and other
charges shall be as specified by RERC.
6.2 The Power Producer may have the facility
of power banking with the Discom. The Discoms at the end of 31st December
of every calendar year, will pay to the Power Producer for the energy billed
into the grid but has remained unutilised (after self use or sale to consumers
/ licensees other than Discoms) by the Power Producer during the said calendar
year at the pooled rate for procurement of power by the Discom in the preceding
financial year.
![]() |
Provided
that, if at the end of the calendar year it is found that the Power Producers
has drawn more electricity than that billed by him into the system, he
shall be liable to pay the cost of the same at the HT tariff prevailing
at the end of the proceeding financial year. |
6.3
The Power Producer shall execute an agreement (Wheeling and Banking Agreement)
with the Discom for such banking. However, the wheeling agreement with RVPN
will be executed separately if the Power Producer intends to use the system
of RVPN for wheeling power.
6.4 WBAs may be allowed to be assigned, in parts,
on one-time basis in each case, to other parties after completion of the project
and its connectivity to the grid, with the consent of RREC & RPVN / Discom(s)
on payment of Rs. 1.00 lac per application to RREC.
7. Price of Power:-
7.1 The price of power to be sold by the eligible
Power Producer to consumers/ licensees other than Discoms will be determined
by the mutual understanding/agreement between the seller and the purchaser.
7.2
For the Discoms the price of such power will be as per the Schedule 1 A /
1 B appended, as the case may be.
Provided
that for wind farms commissioned after March 31, 2007 and for biomass power plants
commissioned after September 30, 2008, the tariff shall be in accordance with
that specified by RERC.
(RERC tariff is enclosed as Appendix-1 & 2)
8.
Power Purchase Agreement:-
8.1 The sale of electricity by Power Producer
to Discoms will be governed by the Power Purchase Agreement executed between
the concerning Discom and the Power Producer and witnessed by RREC.
8.2 The Power Purchase Agreement for wind power
will be for 20 years and for power other than wind power will be for 10 years.
Provided that at the end of the
period of Power Purchase Agreement the new PPA can be executed at mutually agreed
rates
8.3 PPAs may be allowed to be assigned, in parts,
on one-time basis in each case, to other parties after completion of the project
and its connectivity to the grid, with the consent of RREC & RPVN / Discom(s)
on payment of Rs. 1.00 lac per application to RREC
9.
Settlement of Accounts:-
The account of all transactions between the Power Producer and the Discoms/ RVPN
regarding price of power and wheeling charges shall be settled on monthly basis
except in case of price of power under banking arrangements which will be settled
within one month of the closing of every calendar year.
10. Merit order Dispatch :
The power plants commissioned under the Policy would not be subject to Merit order dispatch regulations.
11. Incentive by the State Government:
11.1 Exemption from Electricity Duty: - Consumption of electricity generated by Eligible Power Producers for its captive use or for sale to a nominated third party will be exempted from Electricity Duty @ 50% for a period of 7 years from COD.
11.2 Grant of incentives available to industries: - Generation of electricity from Non-conventional Energy Sources shall be treated as eligible industry under the schemes administered by Industries Department and incentives available to industrial units under such schemes shall also be available to the Power Producers.
11.3 Single Window Clearance: A State Level Empowered Committee consisting of following will provide single window clearance on proposals received for developing the power plants based on Non-Conventional Energy Sources:
1.
Addl. Chief Secretary (Infrastructure) Chairman
2. Principal Secretary, Revenue,
Member
3. Secretary, Energy Member
4. CMD, Rajasthan Vidyut Prasaran Nigam
Member
5. CMD, Rajasthan Renewable Energy Corporation Limited Member Secretary
The
Collector/Collectors in whose jurisdiction the land is proposed for allotment
shall be special invitee.
11.4 Allotment of land on concessional rates:
The Government land required for power projects based on non-conventional
sources of energy shall be allotted to Power Producer at concessional rates
viz, 10% of DLC rates as per procedure prescribed below.
Provided
that -
(a) The site for wind power project will be chosen by the developer after
ascertaining the wind parameters. |
![]() |
12.
RREC to be Nodal Agency: -
RREC will be Nodal Agency for power projects based on non-conventional sources
of energy. It will also play the role of facilitator for:-
(i) Execution of PPA/WBA with RVPN/Discoms
(ii) Loans from IREDA/PFC/REC/Financial Institutions/ Commercial Banks.
13. Registration for Power Project: -
13.1 The Power Producer shall register the application
with RREC in prescribed proforma appended with the Policy along with the required
project report, documents, attachments and the interfacing scheme etc.
13.2 Along with his application, the Power Producer
shall deposit an amount of Rs. 50,000/- per MW with RREC towards processing
fee, which shall be non-refundable.
Provided that in such cases where the applicants had already submitted an
application for a project under Wind Policy 2003, along with processing fees,
and had re-apply for the same project under the new NCES Policy 2004, the
processing fees paid earlier for the same project may be adjusted in the total
processing fees due under the NCES Policy 2004.
![]() |
Provided further that for projects registered from
April 1, 2007 onwards the processing fee chargeable shall be Rs. 25,000/-
per MW. |
Provided that in case such relocation entails additional investment for evacuating the power on the part of RVPN / Discom, the connectivity charges shall be levied as per actuals.

14.1 RREC shall forward land
allotment application for the identified govt. land to the concerned District
Collector within a period of 7 days from the receipt of the application.
14. Approval of Power Projects:
Provided that the land application in case of wind farm can be forwarded only
if the same is for site for which wind parameters are certified by C-WET.
14.2 RREC shall forward the grid interfacing
plan submitted by the applicant to RVPN/Discom for technical acceptance.
14.3 RREC shall issue in principal clearance
for the project on verification of following:-
14.3.1 The plan/layout of the project is strictly
in accordance with standard guidelines of MNRE/C-WET.
14.3.2 The suggested grid interfacing arrangement
as submitted by the applicant is accepted and approved by RVPN/Discom.
14.4 The project proposal "in principle
cleared" by RREC and meeting the above requirements shall be put up before
the State Level Empowered Committee.
14.5 The decision for single window clearance
(approval of project) will be taken by the SLEC within one month.
14.6 The Power Producer would initiate activities
on the identified / allotted land only after approval is granted by the State
Level Empowered Committee.
Provided that if any Power Producer initiates activities on the identified
or the allotted land without project approval, subject to regularization of
land by the competent authority, grid connectivity would be allowed to such
project only after payment of an amount @ Rs. 5.00 lacs per MW as penalty
amount by Power Producer to RREC.
Provided further that if this provision is violated second time by the Power Producer, no grid connectivity would be permitted to such project."
15.
Security Deposit and its forfeiture: -
![]() |
15.1 The Developer/ Power
Producer shall deposit a refundable amount as security deposit with
RREC, towards completion of the project in the prescribed time frame,
within 30 days of the approval of the project by the SLEC in the case
of solar power projects, capacity allocation by RREC in the case of
wind energy projects and as per Clause 16.1 A in the case of biomass
power projects. |
Provided
that:
(1) The amount shall be Rs. 5.0 lacs with effect from April 1, 2007.
(2) For projects up to 25 MW, the security deposit shall be in the form of
cash, on which no interest shall be payable.
(3) For projects exceeding 25 MW, the security deposit may be in the form
of bank guarantee.
(4) If the security amount is not deposited within the time specified, the
approval of the SLEC shall stand withdrawn and priority would be accorded
to the next applicant. For re-submission of the case to SLEC for project approval,
the applicant will have to re-register the case, along with the processing
fee, within the next 30 days, failing which the land allotted shall also stand
cancelled.

For
Biomass energy projects: Rs. 1.0 lac per MW. The security deposit may be in the
form of cash or bank guarantee.
For Solar Power Projects: Rs. 5.0 lac per MW. The security deposit may be
in the form of cash or bank guarantee.
15.3 The timeframe for completion of projects shall be as follows:
|
Project
Capacity
|
Completion
Schedule
|
|
For
Wind Energy Projects (from date of allocation of capacity by RREC)-
|
|
| Up to 25 MW | 6 Months |
| 26 - 50 MW | 12 Months |
| 51 - 75 MW | 16 Months |
| 76 - 100 MW | 20 Months |
| 101 MW & above | 24 Months |
For Bio-Mass Projects (from date of project approval by SLEC)-20 to 28 months.
For Solar Power Projects the time frame for completion of projects shall be as determined by SLEC.
Provided that RREC may extend the time schedule and provide new schedule if:-
a) The Power Producer makes an application giving convincing reasons for delay
in the completion of the project at least 15 days before the expiry of the
prescribed period and the application is accompanied with the amount prescribed
below:
|
Time period
|
Amount payable for extension
|
| One-month extension after the date of scheduled commissioning | Rs.50000 / MW |
| Two-month extension after the date of scheduled commissioning | Rs.100000 / MW |
| Three-month extension after the date of scheduled commissioning | Rs.200000 / MW |
| More than Three month extension after the date of scheduled commissioning | Rs.500000
/ MW |
b) The reasons given by the Power Producer in the application are found convincing.
c) In the case of solar power projects, a request for extension in the original time frame stipulated by SLEC for the completion of the project shall be examined by a committee comprising of Secretary Energy, Government of Rajasthan, Chairman & Managing Director, RREC and Chairman & Managing Director, JVVN & Chairman Discoms. The Committee's recommendation would be placed before the SLEC for appropriate decision in regard to extension of the time period, with either waiver of extension charges or reduction in the amount to be charges for such time extension, looking to the merits of the case and the circumtances beyond the control of the power producer.
15.4 The security deposit shall stand forfeited
by RREC in the event of failure of the Power Producer to adhere to the prescribed
time schedule.
15.5 The allotment of land shall also stand cancelled
if the power project is not completed within the time frame specified in Clause
15.3 of the Policy and the Power Producer shall not be considered for allotment
of land thereafter.
16. Special Concessions/ conditions for Biomass Projects.
16.1 Reservation of Area for biomass collection:
If the State Government is satisfied with the progress achieved in the setting
up of a Biomass based power plant of aggregate capacity of 7.5 MW at a duly
approved site, no other biomass power plant shall be allowed within a radial
distance of 40 KM.
Provided that:
(a) The State Government shall have the right to review the biomass availability
and reduce the reservation area to not less than 30 Kms radius, if it is satisfied
that such reduction in area reservation would not adversely affect the sustainability
of existing plants. However, such review shall be held not before 2011.
(b) Projects cleared under Policy dated 11.3.99 and complying with conditions
laid down vide amendment dated 28.2.03 shall continue to enjoy 50 Km. reservation
facility.
(c) Small capacity biomass based gasifiers being set-up under any programme
of the State Govt. / GOI, through RREC or otherwise, would be allowed to be
set-up within the reserved area so defined as above.
(d) If Eligible Power Producer desires to install lower/higher capacity plant
or wants to enhance the capacity of the power plant above 7.5 MW, the reservation
area could be reduced/ extended by RREC to meet proportionate biomass requirement
for the plant."
16.1A In view of the area reserved for biomass
power plants post-registration, the timeframe for completion of different
activities would be as follows:
· Deposit of Security amount (Rs. 1 lac / MW) - within 1 month of registration.
· Finalization of land and power evacuation plan - within 4 months
from date of registration.
· For non-compliance of above conditions, the registration shall stand
cancelled and the security deposit, if deposited, shall be refunded.
Provided
that extension in time-limit may be granted on submission of application to
RREC, along with convincing reasons, 15 days prior to expiry of the time-limit,
along with penalty amount as follows:
- For extension up to 1 month - @ Rs. 0.50 lacs / MW
- For extension up to 2 months - @ Rs. 1.00 lacs / MW
- No further extension beyond this limit.

16.2
Use of Conventional Fuel : To ensure generation of power in the event of reduced biomass availability
in the district, a Power Producer could be permitted to use conventional fuel
up to 30%, computed on the basis of declared heat rate linked to P.L.F, in
the case of biomass based power plant of the aggregate capacity of 15 MW and
above at a particular location and up to 25%, on similar basis, for those
below that capacity.
16.3
Availability of Water for Power Generation :
The Eligible Power Producers shall be allowed to use water for power generation,
wherever possible. The modifications(s) required, if any, in the existing
canal system shall be done by the Irrigation Department at the cost of the
Power Producer. For use of ground water, specific approval from concerned
authorities shall have to be taken.
17.
Savings:
17.1 Power projects established
under the Policy -1999, Policy -2000 and Policy - 2003 will continue to
be governed as per the terms & conditions already agreed and approved
under the concerned policies. However, renewal of terms & conditions,
if any, will be guided by this Policy or any other Policy prevalent at that
time.
17.2 The power projects for which PPAs have
been signed before the promulgation of this Policy will also be treated
under the terms & conditions of the Policy under which approval was
accorded to the same provided the power projects gets commissioned before
31st March 2005.
Provided that for power projects based on biomass the period of commission
will be up to 30th September, 2008.
17.3 The wind power project proposals for which
RREC has accorded approval, land has been allotted, settings have been approved
by RREC before promulgation of this Policy and substantial investment (50%
of the proposed capital investment) has already been made by Power Producer
will be governed by the Policy-2003.
(Clarification - The limit of 250 MW on PPAs to be signed by Discoms under
Policy-2003 shall be observed by the Committee while considering such cases)
Provided that a committee constituted hereunder will determine whether the
substantive investment has been made:-
i) Principal Secretary, Energy - Chairman
ii) Secretary, Finance, Expenditure - Member
iii) Managing Director, RREC - Member Secy.
Provided further that the committee mentioned above, shall consider only those
cases where the developer/investor has submitted application within 10 days
of the notification of this Policy.
Schedule:
1 A
Tariff Schedule for Non-Conventional Energy
Sources (Clause no.7.2)
|
S.No. |
Financial Year of COD |
Wind * |
Other than wind including Biomass Rs. Per
kWh |
|
1 |
2004-05 |
2.91 |
3.32 |
|
2 |
2005-06 |
2.96 |
3.39 |
|
3 |
2006-07 |
3.01 |
3.45 |
|
4 |
2007-08 |
3.06 |
3.52 |
|
5 |
2008-09 |
3.11 |
3.59 |
|
6 |
2009-10 |
3.16 |
3.65 |
|
7 |
2010-11 |
3.21 |
3.72 |
|
8 |
2011-12 |
3.26 |
3.78 |
|
9 |
2012-13 |
3.31 |
3.85 |
|
10 |
2013-14 |
3.36 |
3.92 |
|
11 |
2014-15 |
3.36 |
3.92 |
|
12 |
2015-16 |
3.36 |
3.92 |
|
13 |
2016-17 |
3.36 |
3.92 |
|
14 |
2017-18 |
3.36 |
3.92 |
|
15 |
2018-19 |
3.36 |
3.92 |
|
16 |
2019-20 |
3.36 |
3.92 |
|
17 |
2020-21 |
3.36 |
3.92 |
|
18 |
2021-22 |
3.36 |
3.92 |
|
19 |
2022-23 |
3.36 |
3.92 |
|
20 |
2023-24 |
3.36 |
3.92 |
Schedule:
1 B
Tariff Schedule for Wind Energy (Clause no.7.2)
(For Projects Commissioned after February
23th 2006)
|
S. No. |
Financial
Year of COD
|
Rs. / kWh |
|
1. |
2005-06 |
3.25 |
|
2. |
2006-07 |
3.31 |
|
3. |
2007-08 |
3.37 |
|
4. |
2008-09 |
3.43 |
|
5. |
2009-10 |
3.49 |
|
6. |
2010-11 |
3.55 |
|
7. |
2011-12 |
3.61 |
|
8. |
2012-13 |
3.67 |
|
9. |
2013-14 |
3.73 |
|
10. |
2014-15 |
3.79 |
|
11. |
2015-16 |
3.79 |
|
12. |
2016-17 |
3.79 |
|
13. |
2017-18 |
3.79 |
|
14. |
2018-19 |
3.79 |
|
15. |
2019-20 |
3.79 |
|
16. |
2020-21 |
3.79 |
|
17. |
2021-22 |
3.79 |
|
18. |
2022-23 |
3.79 |
|
19. |
2023-24 |
3.79 |
|
20. |
2024-25 |
3.79 |
|
21. |
2025-26 |
3.79 |
Tariff
for wind projects (As per RERC order 09-03-2007)